February 23, 2018 – The City of Midland Engineering Department is ramping up for another busy construction season in 2018 with a variety of street reconstruction, resurfacing, and water main replacement projects on this year’s list.
High-traffic streets scheduled to undergo reconstruction include Eastman Avenue at W. Wackerly Street, Waldo Road from Bay City Road to S. Saginaw Road, Waldo Avenue from E. Ashman to Wheeler, Airport Road from Dublin Avenue to Perrine Road, and W. Wheeler Street from N. Saginaw Road to Jefferson Avenue. The City anticipates street and lane closures during projects, and detours will be posted if necessary.
Street construction activities will also take place at several other locations, including E. Carpenter Street, W. Chapel Lane, Gibson Street, Richard Court, Manor Drive, Sayre Street, St. Nicholas Street, and Orchard Drive from W. Sugnet Road to Main Street. General work includes curb replacement, sidewalk repairs, water main replacement, and street paving activities.
A current list of City projects and their estimated months of start and completion is below.
For more information, contact City Engineering at 989-837-3348 or view project updates and an interactive project map at http://bit.ly/midlandroads. Residents may also receive updates on the City of Midland Facebook page at facebook.com/cityofmidlandmi, on Twitter at @CityofMidlandMI, by subscribing to the City’s weekly e-newsletter at http://bit.ly/cityhallnews, or via the “Notify Me” feature on the City’s website at www.cityofmidlandmi.gov.
City of Midland 2018 Construction Projects
Project | Project Limits | Project Description | Estimated Start | Estimated Completion |
E Carpenter St | Ashman to Patrick | Street Reconstruction/Water Main Replacement | May | August |
Eastlawn Dr | Washington to Swede | Street Reconstruction | June | August |
W Chapel Ln | Jefferson to Nakoma | Street Reconstruction/Water Main Replacement | May | August |
Waldo Ave | E Ashman to Wheeler | Street Reconstruction/Water Main Replacement | May | August |
W Wackerly St Water Main | Sturgeon Creek to Sturgeon | Water Main Bore | May | June |
Cambridge St Water Main | Washington to 900' West | Water Main Replacement | April | May |
Airport Rd | Dublin to Perrine | Street Reconstruction | May | July |
S Waldo Rd | Bay City to S Saginaw | Street Reconstruction/Traffic Signal Upgrades | May | August |
Sayre St | Eastman to Jerome | Street Reconstruction/Water Main Replacement | May | July |
St Nicholas St | W Main to W Buttles | Street Reconstruction/Water Main Replacement | May | July |
Main St Streetscape | Cronkright to Poseyville Bridge | Streetscape | June | July |
Pershing, Barth, Bayliss | Austin to Patrick | Street Reconstruction/Water Main Replacement | June | September |
W Collins St | Adelaide to Ashman | Street Reconstruction | June | September |
Eastman Ave | W Wackerly to North | Street Reconstruction | July | September |
Manor Dr | Helen to N Saginaw | Street Reconstruction/Water Main Replacement | July | October |
Orchard Dr | W Sugnet to W Main | Street Reconstruction | July | September |
Richard Ct | Manor to End | Street Reconstruction/Water Main Replacement | July | October |
Surface Treatment Program | Various Major & Local Streets | Crack Filling/Chip Seal/Slurry Seal/Micro-Surfacing | July | September |
Gibson St | Sturgeon to Drake | Street Reconstruction | August | October |
W Wheeler St | N Saginaw to Jefferson | Street Reconstruction | August | October |
Pomranky Rd | Vance to East | Intersection Improvements | September | September |
S Saginaw Rd | Dartmouth to E Patrick | Street Resurfacing | October | November |
Water Main River Crossing | Farmers Market to Crissey | Water Main Bore | October | November |