News Flash

News Carousel

Posted on: February 25, 2022

City Construction Schedule Announced for Spring, Summer 2022

Orange traffic cones on a blue sky

February 25, 2022 – The City of Midland Engineering Department is ramping up for another busy construction season in 2022 with a variety of street reconstruction, resurfacing, and water main replacement projects on this year’s list.

Planned high-traffic improvements include street reconstruction projects on Jefferson Avenue from Sugnet Road to Wheeler Street; W. Wackerly Street from Partridge Lane to Sturgeon Avenue; and Waldo Avenue from James Savage Drive to Bay City Road.

Projects on local streets include street reconstruction and water main replacements on E. Pine Street from Rodd Street to George Street, Woodbridge Lane from Brambleridge Lane to Moorland Drive, Brambleridge Lane from Woodbridge Lane to Sutton Place, Cortland Street from Brookfield Drive to the end of Cortland Court, and North Street from George Street to Jefferson Avenue.

In addition, crews will begin a street extension project that will create a new section of roadway on Sugnet Road from Main Street to Northwood Drive. This project is expected to begin in May 2022.

The City anticipates street and lane closures during projects, and detours will be posted if necessary. A complete list of 2022 City projects and their estimated months of start and completion is below. 

ProjectProject LimitsProject DescriptionEst. StartEst. Completion

Pine St.

Rodd to George

Street Reconstruction & Water Main Replacement

May

August

North St.

George to Jefferson

Street Reconstruction

May

August

Soccer Drive Water Main

Swede to Jefferson

Water Main

May

September

Jefferson Ave.

Sugnet to Wheeler

Street Reconstruction

May

September

Surface Treatment Program

Various Major & Local Streets

Crack Filling/Chip Seal/Slurry Seal

May

September

Sugnet Road Extension

Main to Northwood

Street Extension 

May

September

Stark Road Culvert

Stark Rd. @ State Drain

Culvert Replacement

May

November

Brambleridge Ln.

Sutton to Woodbridge

Street Reconstruction & Water Main Replacement

July

October

Woodbridge Ln.

Brambleridge to Moorland

Street Reconstruction & Water Main Replacement

July 

October

Sutton Pl.

Brambleridge to End

Street Reconstruction & Water Main Replacement

July 

October

Dilloway Drive

Drake to Campau

Street Reconstruction

July 

October

Cortland St.

Brookfield to End

Street Reconstruction & Water Main Replacement

July 

October

Waldo Ave.

James Savage to Bay City

Street Reconstruction

July

September

Wackerly St.

Partridge to Sturgeon

Street Reconstruction

July

October


For more information, contact City Engineering at 989-837-3348. Project updates will be made available during construction season at http://bit.ly/midlandroads. Residents may also receive updates on the City of Midland Facebook page at facebook.com/cityofmidlandmi, on Twitter at @CityofMidlandMI, or via the “Notify Me” feature on the City’s website at www.cityofmidlandmi.gov

Facebook Twitter Email

Other News in News Carousel

New City Clerk Lacey Todd

Lacey Todd Promoted to City Clerk

Posted on: April 8, 2022
A black MPD SUV sits on green grass in front of the Tridge on a sunny day

MPD Awarded Grant for 3D Scene Scanner

Posted on: January 7, 2022
Red fire hydrant in a yard

Adopt a Hydrant This Winter

Posted on: January 7, 2022
4 toy cars parked in a square around yellow lines in a parking lot

On-street Parking: Rules of the Road

Posted on: November 12, 2021