Posted on: March 23, 2023

[ARCHIVED] Concept 5 Sewer Upsizing Project to Begin April 3 on Sugnet Road

Beginning Monday, April 3, W. Sugnet Road will be closed to through traffic from W. Main Street to Valley Drive as construction begins on a multi-year sewer pipe upsizing project through the Concept 5 Sewer Improvement Plan.

When completed, this project will increase the size of 8,000+ linear feet of sanitary sewer pipe along Perrine Road, Saginaw Road, Main Street, and W. Sugnet Road. This pipe upsizing will coincide with street reconstruction and water main replacement work, with road closures and construction activities similar to any other City road construction project.

As this is an extensive project spanning multiple construction seasons, work will be completed in phases as outlined below:

  • Phase 1:        Sugnet Road from W. Main Steet to Valley Drive. Sugnet Road will be closed to through traffic and local traffic will be maintained for the duration of construction in this phase.
  • Phase 2: W. Main Street from Sugnet Road to Saginaw Road. Main Street will be closed to through traffic and local traffic will be maintained for the duration of construction in this phase.
  • Phase 3: Saginaw Road from W. Main Steet to Perrine Road. Westbound Saginaw Road will be closed and traffic detoured for the duration of construction in this phase. Eastbound traffic will be maintained for the majority of construction in this phase. During sanitary sewer placement in the eastbound lanes, a complete road closure will be in effect for a short duration.
  • Phase 4: Perrine Road from Saginaw Road to Moorland Drive. Perrine Road will be closed to through traffic and local traffic will be maintained for the duration of construction in this phase.

Work on areas of the project after Phase 1 will not begin until substantial completion of the previous phase has occurred. The entire upsizing project is estimated to be completed in June 2024.

Residents are reminded that due to the nature of construction activities, the information provided may change at any time. Should an issue arise that would change this schedule, the City will provide updates online at www.cityofmidlandmi.gov/concept5 and via its Facebook and Twitter channels at @CityofMidlandMI. 

For more information on the Concept 5 Sewer Improvement Plan and planned projects related to this plan, including a link to sign up for email updates on each project, visit www.cityofmidlandmi.gov/concept5

Facebook Twitter Email

Other News in News Releases

Shane Bjorge Named City Engineer

Posted on: February 16, 2024

Apply for a Circle Community Garden Plot

Posted on: February 2, 2024

Adopt a Hydrant This Winter

Posted on: January 11, 2024

Winter 2023 Tax Bills Mailing in December

Posted on: November 17, 2023

Reminders of City Parking Rules

Posted on: November 9, 2023

City to Recognize Beautification Efforts

Posted on: October 27, 2023

DPS Reminds You to Shake Your Mailbox

Posted on: October 13, 2023

Spray Parks to Close for the Season

Posted on: September 28, 2023

Pedestrian Plazas Close for the 2023 Season

Posted on: September 28, 2023

Help Keep Waterways Clean This Fall

Posted on: September 22, 2023

Remove Decorations from Midland Cemetery

Posted on: September 15, 2023

Taglauer Named Code Official of the Year

Posted on: October 21, 2022

Reminders of City Signage Ordinance

Posted on: October 7, 2022

City Promotes John Jurek to Fire Marshal

Posted on: September 2, 2022

Lacey Todd Promoted to City Clerk

Posted on: April 8, 2022